New accomodation block - now open 01/05/21

 
 
Demolision and clearance underway

Demolision and clearance underway

Ground work and site clearance

The digger makes light work of demolishing and clearing the site, a few hours in fact. This was a huge time saver as this would have taken well over a week by hand!

To keep costs down bricks will be cleaned and reused where ever possible.

I think this was the first JCB some of the children had ever seen… they were very excited!


Foundation stone

Brenham and wife lay the foundation stone 01/04/19.

There was a palpable feeling of thankfulness and joy to a long awaited answer to prayer as work begins on the new building after a lengthy period of faithful stewardship and hard saving.

Building work begins

Building work begins


Hard at work constructing main steel and concrete pillers

Hard at work constructing main steel and concrete pillers

Bricks, steel and

100 sacks of cement = $500, 1 ton of steel - $900, 10,000 bricks - $900

Total basic frame cost = $2300

Reserves in hand = $4000

Please give generously to cover roofing, internal fixtures and fittings, as well as new beds, wardrobes, curtains, fridges, fans….